lock iconSchedule Management

A network diagram has been created to help the team to determine the schedule baseline. You, the project manager, added the time estimates for each activity to establish the critical path for the project. It's been discovered that the project has three critical paths. Which of the following choices best describes how the project will be affected by this discovery?