Cause-and-effect diagramming was used to review the issues that happened during testing. Coordination of the interrelationships of deliverables has improved. Also some efficiencies were discovered and shared with other teams. Stakeholders believe that control efforts and reporting on future projects will be easier. Earned value analysis is the basis for which of the following?