PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconIntegration Management

When project managers perform integrated change control, they review all change requests and approve or reject them. You are the project manager for your organization. When it comes to integrated change control, you must ensure that which one of the following is present?