PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconIntegration Management

A project manager is overseeing a project to construct the largest tennis court in the city. He is in the process of Develop Project Charter to develop a document to formally authorize a project or a phase and identify the business objectives, understanding of stakeholders' expectations and the new product that it's intended to satisfy. Which of the following is NOT an input to this Develop Project Charter process?