Procurement Management
You are managing a construction project to build a bridge. Yesterday you negotiated all terms and conditions with a selected vendor. Both parties are fully satisfied with the outcome of the negotiation, therefore, you started working on the draft official letter of notification of the contract award. At the moment you are in the