Scope Management
Prior to creating the project charter, the project manager held a few meetings with the sponsor and stakeholders. In one of the meetings, the sponsor specifically denied funding for one specific item. Two stakeholders requested the project manager add work for the item which was denied by the sponsor. What should the project manager do in this situation?