PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProcurement Management

Claude is a project manager and he has been assigned to to a project on the design and development of a new skin cleansing device. After gaining agreement that the procurement statement of work is complete, Claude has doubts about whether it really addresses all the buyer's needs. He is about to attend the bidder conference. What is the best thing for him to do in regards to the session?