lock iconProject Management Responsibility

So far, your project has been running true to its baselines. However, you've discovered a serious mistake in the implementation plan that will prevent you from meeting a milestone date. The milestone in question is not on the critical path, but it's on a near-critical path. A meeting where you will be delivering a routine status report is scheduled in two days. The best course of action for you, the project manager, is to: