The project manager is making ongoing formal and informal assessments of the team's performance while project work is being done. The results of team assessments are used to recognize the team's prog­ress and to motivate improvement. His main goal is to identify specific training and assistance to improve the team's performance. At the current stage of the assessment, the project manager is focused on the analysis of how much team members’ skills have improved over the course of the project and how well the team is performing, interacting and dealing with conflicts. Which of the following is the project manager performing?