PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconResource Management

Today you had a meeting with the team regarding the equipment needed for the project. It has been determined that the team will need a very specialized thermostat for the period of at least three months. The company has one thermostat of that kind, however, it's needed for another project. Buying another thermostat is assumed to be cost-prohibitive. The least effective action for the project manager to take is: