PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

You, the project manager, make some changes to the project management plan. Soon you will have a meeting with the sponsors to get approval. Recently there have been issues with the projects because they were started quickly and it was assumed that there would be few changes. The sponsors will need to be persuaded that this project won't have similar issues. You've done a lot of work so far: planned the project, evaluated the approach, planned how you will manage risks etc. There are a few minor risks on the watch list. What, if anything, should be done with those risks?