You are currently managing a project with the cost performance index (CPI) of 0.6 and the schedule performance index (SPI) of 0.72. The project is being completed over a four-year period and there are 627 work packages. Unfortunately, the project did not receive enough support for planning and the team members are inexperienced. It's best if you: