lock iconRisk Management

You are managing a project to develop a new payroll system for your company. You decide to survey the experts within your organization on any foreseeable risks with structure, design and intent of the new software with an anonymous form. You later send out subsequent anonymous surveys to a group of experts with the collected information. This is an example of which of the following?