Risk Management
You are managing a large project and everything has been going well so far. During project executing, the most experienced designer whose work is required for the project gives a two weeks' notice. He has been invited to work for a bigger company and he accepted the offer. This is a major problem which was not included in the risk register. The first thing you should do is: