PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

You are managing a project on a new drone accessory. The sponsor has made a long list of requirements. The product must adhere to high quality standards and be ready in time for image show which will take place in half a year. The sponsor promised to provide all necessary resources to complete the project within these constraints. Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources available, the best thing to do would be: