You've been informed by one team member that a work package will most likely require 9 weeks to complete. If nothing unexpected happens, in the best case scenario, it will take 7 weeks. Since that team member is involved in a few projects, this specific work package may take 17 weeks to complete. What is the correct estimated time to complete the work package?