PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

You've been informed by one team member that a work package will most likely require 9 weeks to complete. If nothing unexpected happens, in the best case scenario, it will take 7 weeks. Since that team member is involved in a few projects, this specific work package may take 17 weeks to complete. What is the correct estimated time to complete the work package?