The project manager overseeing the City Hall renovation is in the Sequence Activities process. He decides to use a software tool to create a Precedence Diagramming Method (PDM) network diagram. It creates a schematic display of the sequential and logical relationships, dependencies and order in which activities must be performed. Also, the project manager added the duration of each activity in the network diagram to calculate the critical path. Which of the following statements about the critical path is FALSE?