Schedule Management
You are managing a project to renovate a historic hall in the university. You've requested two architects, three designers and five construction workers. Today you found out that the management approved only six team members for the project. Which of the following will you use to produce a resource-limited schedule by letting the schedule slip and cost increase in order to deal with resource constraints?