Your organization operates in a matrix environment and utilizes a project management office to structure projects. You are the project manager of a new software development project. This project has 105 stakeholders and will last for two years. One of the project stakeholders informs you that two of his employees will be leaving the organization and will no longer be available as resources on your project. In addition to the project staffing management plan, you should update: