lock iconRisk Management

You are managing projects in an amusement rides company and you are overseeing projects to plan, design and build theme park rides. Your current project is to design and build a steel coaster that will probably be the tallest and fastest coaster in the world. Until recently, the work has been progressing as planned, however, a few days ago you were informed that an unexpected major problem occurred that was not included in the risk register. At it turns out, this issue will add costs to the project. The first thing you have to do is: